Uganda Martyrs University Institutionalnal Repository (UMU-IR)
    • Login
    View Item 
    •   UMU Dissertations
    • Faculty of Business Administration and Management
    • Master of Business Administration
    • Master of Business Administration (Dissertations)
    • View Item
    •   UMU Dissertations
    • Faculty of Business Administration and Management
    • Master of Business Administration
    • Master of Business Administration (Dissertations)
    • View Item
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Project management and power grid expansion at Uganda electricity transmission company limited (UETCL)

    Thumbnail
    View/Open
    Nicholas Kamali Katushabe_BAM_MBAM_2017_ Godfrey Bwanika.pdf (1.206Mb)
    Date
    2017-01
    Author
    Katushabe, Nicholas Kamali
    Metadata
    Show full item record
    Abstract
    This research investigated the relationship between project management and power grid expansion at Uganda Electricity Transmission Company Limited (UETCL). The study objectives were to; establish the relationship between project scope management and power grid expansion at UETCL, identify the relationship between project cost management and power grid expansion at UETCL and establish the relationship between project time management and power grid expansion at UETCL. The study adopted a cross sectional survey research design and adopted both quantitative and qualitative approaches. Data was collected using both questionnaires and interviews from a sample of 92 respondents and documents review. The study findings revealed that there is a significant positive relationship between project scope management and power grid expansion revealed at 0.520**, there is a positive relationship between project cost management and power grid expansion confirmed at 0.654**and there is a positive relationship between project time management and power grid expansion at UETCL which was confirmed at Pearson’s correlation coefficient of 0.622**. The study recommends that; project managers should maintain a project Log of all request for changes including approved and not approved changes with their justifications. It is also recommended that cost estimating process must consider whether the cost of the additional design work will offset the expected savings. This study also recommends that activities must be sequenced accurately in order to support later development of a realistic and achievable schedule
    URI
    http://dissertations.umu.ac.ug/xmlui/handle/123456789/607
    Collections
    • Master of Business Administration (Dissertations) [170]

    UMU_DR copyright © 2022-2025  UMU_IR
    Contact Us | Send Feedback

    UMU_Library
     

     

    Browse

    All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

    My Account

    LoginRegister

    UMU_DR copyright © 2022-2025  UMU_IR
    Contact Us | Send Feedback

    UMU_Library